Border Environment Cooperation Commission
Wastewater
System Improvements in Bisbee, Arizona
1.
Type
of Project.
The project falls under BECC priority areas of
wastewater treatment. A new wastewater treatment plant is under design and will
be constructed to replace the existing wastewater treatment facilities. The units will expand the current treatment
facilities capacity and provide advanced treatment capabilities. The addition of a force main and gravity
conveyance main will be necessary to enable the consolidation of all existing
treatment facilities to one facility.
The proposed upgrade and replacement of the existing treatment
facilities is required due to the fact they are not capable of accomplishing
the State of Arizona Aquifer Protection Program nutrient removal
requirements. Collection system
improvements other than the force main and conveyance main mentioned above,
will consist of replacing or rehabilitating the most deteriorated sections of
the system.
2.
Location of Project.
Bisbee, Arizona is
located in Cochise County, about four miles from the international border with
Mexico. The City of Bisbee is located
in the foothills and canyons of the Mule Mountains. The City limits encompass 5.4 square miles and include three main
developed areas: Old Bisbee, Warren and San Jose and a number of smaller
communities. Physical characteristics
such as topography and geology separate the three developed areas from each
other. The intersection of U.S. Highway
80 and State Highway 92 is southeast of Old Bisbee. Warren is southeast of Old Bisbee; U.S. Highway 80 runs through
the northern portion of Warren. San
Jose is directly south of Old Bisbee, and is divided by the Bisbee-Naco
Highway.
Old Bisbee was
developed within Tombstone Canyon and Brewery Gulch, and then up the steep Mule
Mountain slopes. Retaining walls,
networks of stairways and narrow winding roads are common in Old Bisbee. Many streets and alleys have grades over 30
percent. Warren was developed at the
base of the Mule Mountains on gentler slopes (i.e., about 5 percent or
less). Warren was developed as a
neighborhood layout including parks.
San Jose was developed in the prairie at the foothills of the Mule
Mountains. This area is relatively flat
and gradually slopes north up toward the Mule Mountains with an average grade
of about 2 percent.
Based on information
contained in the 1996-2006 General Plan, the Bisbee area has an annual mean
temperature of 60.5 degrees Fahrenheit.
Temperature extremes range from 15 to 99 degrees Fahrenheit. Heavy
summer rains mark Bisbees climate with almost half of the areas annual
precipitation being in July and August.
Precipitation averages about 17 inches per year, according to the Plan.
The following figure presents the location of Bisbee, Arizona.
3.
Description of Project and Tasks.
a. Project Description
The project evaluated
the condition of the collection system in Bisbee and the course of action
needed to replace or rehabilitate the sewer lines, depending on where the
greatest needs for this existed. Four
alternative courses of action and a no action alternative were evaluated for
the wastewater treatment plants (WWTP), with accompanying capital and operation
and maintenance (O&M) costs.
Generally the existing
wastewater collection systems in Old Bisbee and Warren are in poor condition.
They consist of sewers primarily constructed of vitrified clay pipe (VCP) in
the early 1900's, and are past their useful life. Problems include: undersized, deteriorated pipes, sections of
pipe at grades too steep or too flat, root intrusion, sediment or obstructions
such as grout at the joints, significant numbers of reported back-ups and
sanitary sewer overflows, improper location of manholes, and lack of manholes
or cleanouts at change of grade and/or direction.
The existing
collection system in San Jose was constructed in the mid 1980s. The City has indicated the San Jose system
operates well and without major or recurring problems compared to sewer systems
in Old Bisbee and Warren.
An evaluation was
performed on the Old Bisbee and Warren collection systems. Tasks included Closed Circuit Television
(CCTV) condition assessment of the sewer lines, developing an electronic model
of the sewer system to evaluate wet and dry weather flows, determining the
priority and appropriate sizing of lines to be repaired and/or replaced,
evaluation and recommendation of upgrade and consolidation of treatment
facilities, and determining construction and O&M cost estimates for the project. The majority of the sewer systems in Old
Bisbee and Warren have been documented with CCTV to analyze the extent of
deterioration and prioritize future repairs.
The Citys collection
system in the Old Bisbee and Warren areas experience excessive inflow and
infiltration (I/I). The I/I condition
results in sanitary sewer overflows and a violation of treatment plant quantity
and quality capacities, culminating in releases of raw or partially treated
sewage to the environment.
Wastewater treatment
is conducted at three separate facilities, one for each of the three population
centers. The treatment facilities vary
in age and condition, and the City has difficulty maintaining compliance with
permits and current regulatory standards.
For example, the Mule Gulch WWTP is not designed to remove metals from
the influent, and in the past the facility has been in violation of the
allowable metals effluent mass loading or effluent concentrations for a variety
of metals under its National Pollutant Discharge Elimination System (NPDES)
permit. The City received a Finding of
Violation and Order for Compliance from the Environmental Protection Agency
(EPA) on June 8, 2000. The letter noted
that violations consist of three unreported monitoring results for lead and copper
and excess of the allowable discharge limits for selenium, chromium, lead,
copper, mercury and cyanide. A new
NPDES permit for the Mule Gulch WWTP was issued to the City effective June 24,
2002. In this permit, effluent
standards for metals were adjusted to reflect the actual hardness of the
wastewater stream. The facility is now
generally in compliance with current NPDES permit requirements, however issues
with concentration and mass loading for some metals remain, especially during
periods of high I&I. Additionally,
the Warren lagoons have no liners and the San Jose lagoons have damaged liners,
which will allow percolation of untreated sewage into the aquifer. Neither lagoon facility is permitted, which
creates compliance issues with the Arizona Department of Environmental Quality
(ADEQ) if left uncorrected.
Presently, the City is
operating under a consent order issued by ADEQ to address the I/I
problems. On September 9, 1996, the
City entered into Consent Order P-96-96 with ADEQ to obtain approved Aquifer
Protection Permits for the Warren WWTP and the San Jose WWTP as well as
complete repairs on the collection and conveyance system to eliminate untreated
or partially treated sewage discharges caused by excessive system I/I during
periods of heavy precipitation. The
order also placed a moratorium on connections of any type to the Mule Gulch and
Warren Sewer Systems until corrective action on the I/I issues was taken. The Consent Order required completion of
these tasks by September 9, 2001, and many tasks were completed however the
City and ADEQ concluded in 1999 that the City did not have sufficient resources
to fully meet the 2001 compliance deadline imposed by the order.
On April 14, 2001, the
City entered into a new Consent Order (P-54-01) with ADEQ. This action replaced the 1996 order and
requires completion of collection system improvements identified in alternative
4 of the City 2001 Wastewater Master Plan (City of Bisbee 2001); construction
of a new San Jose WWTP with secondary treatment, denitrification and
permittable disposal capabilities (also identified in alternative 4 of the 2001
Wastewater Master Plan); and submittal of an Aquifer Protection Permit (APP)
application for an expanded and improved San Jose WWTP. Consent Order P-54-01 also continues the
moratorium on new connections to sewage collection systems in Old Bisbee and
Warren areas enacted with the 1996 order.
The proposed project
involves the rehabilitation or replacement of the existing Mule Gulch trickling
filter WWTP, and Warren and San Jose lagoons, combined with the construction of
a new activated sludge plant at the San Jose WWTP site. In addition to
resolving the existing plants deficiencies, the new plant will have increased
capacity that can provide preliminary, secondary and advanced treatments to
accommodate the needs of the community for a minimum of twenty years from the
date of completion. Furthermore, the new facilities will provide an enhanced
disinfecting process. The new treatment process will allow the plant to acquire
an APP and to meet APP standards. The proposed treatment is intended to achieve
the required reduction of polluting substances in the discharged effluent to
within the anticipated permit limits not set yet by EPA and ADEQ. The proposed project will provide the City
with wastewater treatment capabilities that meet local and regional
environmental and human health standards as regulated by ADEQ. Rehabilitation
of the most deteriorated sections of the existing collection system will also
be achieved by this project.
b. Program of Project Work Tasks
Currently, final
design for the wastewater treatment plant and collection system is underway.
Seventy percent design has been completed to date. The 100 percent submittal
will be completed in October 2003.
c. Description of the Community
i. Demographic Information The resident
population is composed of people that live year-round in Bisbee. The study area has seen rapid swings in its
population. From 1930 to 1950, the
population of Old Bisbee dropped from 8,023 to 3,801. In 1960, the Warren and San Jose areas were annexed, bringing the
total City population to 9914. The 1980
Wastewater Master Plan projected the population to be over 15,000 in 2000. However, the area population declined and
recent population projections provided by the U. S. Bureau of Census show a
relatively slow growth curve with the permanent population projected at 6,692
in 2020 and 6,856 in 2040. The most
recent population estimate is 6,090 (April 2000).
In addition to its own
historical significance, the area is well known for its scenic attractions and
special events, including concerts, fine arts shows, and retirement
opportunities. The City currently
serves as a hub to other tourist attractions in the area. This, combined with the mild weather, makes
it a popular place for tourists and seasonal snowbirds. An estimated 1,500 tourists and snowbirds
visit the area each day with that number projected to increase to 2,500 by the
year 2020.
ii. Local Environmental Services The City of
Bisbee owns its wastewater treatment facilities. The three wastewater facilities provide service to most of the
community except those on individual septic systems. The City estimates that there are presently approximately 1,190
individual septic systems in the study area, most of which are located in the
San Jose area. Water service is
provided by Arizona Water Company (AWC).
Water is supplied from groundwater wells located west of Naco, Arizona.
Most residents are connected to the water system except for some private well
owners. Solid waste is hauled to the
Cochise County Western Regional Landfill.
iii. Project alternatives Gannett Fleming, under
contract to the BECC, prepared a Waste Water Master Plan to evaluate the
condition of the collection system and four (4) treatment alternatives for the
Citys WWTPs.
Collection System
Various deficiencies
in the collection system have been noted by ADEQ during site inspections since
1996. The most significant of these are
excessive inflow and infiltration (I/I) in the two older areas of the City; Old
Bisbee and Warren. As a result of the
inspections, ADEQ issued a Consent Order for the City to address collection
system deficiencies. ADEQ also noted
various deficiencies in the three (3) wastewater treatment plants serving the
City. Based on the noted deficiencies,
EPA recently issued a Finding of Violation and Notice for Compliance to address
effluent violations from the Mule Gulch treatment plant.
A condition assessment
was performed on the collection system.
The condition assessment consisted of obtaining and reviewing as-built
maps of the existing system, performing CCTV of the sewer mains and inspection
of manholes. Alternative methods for
rehabilitation or replacement of the sewer mains and manholes were evaluated
based on the condition and location of the facilities. Based on the evaluations, recommendations
were made for the rehabilitation or replacement of the sewer mains and
manholes. The recommendations for sewer
mains and manhole rehabilitation were prioritized in four (4) phases over a
ten-year period.
The San Jose sewer
system has never been CCTV inspected.
Therefore, as part of the Master Plan, an allowance was included for the
CCTV inspection of the San Jose sewer system and for rehabilitation or
replacement of sewer mains over a 20-year period.
The following options
were evaluated for prioritizing the rehabilitation or replacement of the sewer
mains:
1. Prioritize by drainage area and perform
rehabilitation on all components within a drainage area.
2. Prioritize by drainage area and perform
rehabilitation on selected components within a drainage area.
3. Prioritize by sanitary sewer segments and
perform rehabilitation on upstream components.
4. Prioritize by sanitary sewer segments and
perform rehabilitation on selected upstream components.
Options 1 and 3 were
eliminated, as they require completion of a private sewer investigation program
prior to performing the repairs to a majority of the public sewer
components. Hence additional costs for
developing, and time for implementing, a private sewer program combined with
the delay of performing repairs to the public sewers, render these options
detrimental to a cost-effective and timely rehabilitation program.
Option 2 was eliminated
based on the widespread incidences of sanitary sewer overflows and the
deteriorated condition of the sewer system throughout all drainage areas. While the selection of Option 2 would allow
for effective rehabilitation of components within selected drainage areas, it
would also delay rehabilitation of selected components in more-desperate need
of repair, and possibly compound problems in downstream components that have
not yet been rehabilitated.
Option 4 was selected
since it most efficiently addresses system-wide priorities. This option of performing rehabilitation on
sanitary sewer segments and selected upstream components should be taken
several steps further. For instance,
rehabilitation should be performed in phases, combining high priority sewer
segments with high-ranking drainage areas.
In addition, one or more areas should be designated as pilot areas for a
private sewer investigation program.
Observation tees would need to be installed in the vicinity of service
laterals and a mini-camera used once tees are installed. Recommendations for private sewer
rehabilitation would be made based on the outcome of the pilot study.
Wastewater Treatment
The no project, or
do-nothing, alternative was evaluated and considered not to be a viable option
due to the growing environmental and health risks, as well as the Notice of
Violation and Consent Order from the State of Arizona and Finding of Violation
from EPA.
The condition,
operation and maintenance of the existing wastewater treatment and disposal
facilities were evaluated and recommendations made for their abandonment,
rehabilitation or replacement. The four
alternatives were reviewed to meet the present and anticipated State and EPA
permit requirements.
The four treatment
options were developed, given the conditions that exist in Bisbee which create
challenges that are not likely to be found in most other communities. Topography and geology have a great bearing
on treatment alternatives. Other factors include age of the existing system,
condition of the existing treatment facilities and the ability of the City to
acquire necessary land, as well as issues brought up by the mining history of
Bisbee, such as the sulfate plume in the San Jose area.
If none of the
alternatives of this project are implemented, many adverse effects will occur
to the community. The groundwater could
potentially begin to deteriorate which will create a public health issue as the
City currently receives its water from a rather limited source. The condition of the collection system has
possibly contributed to the Mule Gulch WWTP to violate its NPDES permit for
some metals, which in turn deteriorates the surface water of Mule Gulch.
Alternative 1
Maintain All Three Wastewater Treatment Facilities in Service
The purpose of
alternative 1 is to evaluate the cost of keeping all three treatment facilities
open while minimizing the need to expand the treatment facilities and/or
disposal areas and the need to transfer wastewater between facilities. It assumes that the discharge permit limits
for metals in Mule Gulch's NPDES permit can be increased or that the
rehabilitation of the sewer mains reduces the metals entering the WWTP such
that Mule Gulch is granted an APP by the State and the Finding of Violation is
resolved so that the WWTP can continue to discharge to Mule Gulch.
Alternative 1 involves
constructing a lift station at the Mule Gulch WWTP and a force main along
Arizona Street to convey excess flows to the Warren system, and expanding the
existing lagoons at Warren and San Jose to treat future flows. Effluent would be disposed of from the Mule
Gulch WWTP to Mule Gulch and from Warren and San Jose by reuse systems.
Alternative 2 Close
Mule Gulch and Divert Flows to Warren; San Jose Remains in Service
The purpose of
alternative 2 is to evaluate the impact of closing the Mule Gulch facility and
pumping those flows to the Warren facility.
The Warren and San Jose lagoons would be left in service and expanded to
treat the respective additional wastewater flows. The additional flows would
require purchase of additional land at Warren to dispose of the flows by reuse.
Alternative 3
Treatment Plants at Warren and San Jose
Alternative 3
evaluates the wastewater treatment system with Mule Gulch taken out of service,
flows diverted to Warren, and nitrification/denitrification activated sludge
wastewater treatment facilities installed at the Warren and San Jose
sites. The
nitrification/denitrification process will remove the nitrogen from the
wastewater. The resulting effluent will
meet the requirements for surface disposal of the effluent because of the low
nitrogen concentrations. Using surface
disposal for the effluent allows more effluent per acre to be applied to the
land than is allowed by reuse. This
means less land is required. In
addition, ADEQ does not require storage ponds when surface disposal is
used. Even with surface disposal,
additional land needs to be acquired for disposal of the effluent from the
Warren facility.
Alternative 4 One
Treatment Plant at San Jose
In alternative 4, both
Mule Gulch and the Warren treatment facilities are taken out of service and the
corresponding flows diverted to the San Jose site. The Mule Gulch flows would be conveyed to Warren via a lift station
and force main along Arizona Street.
The Warren flows would be conveyed to the San Jose site via a pipeline
along the Airport Highway.
Nitrification/denitrification activated sludge wastewater treatment
facilities would be installed at the San Jose site. As in alternative 3, the nitrification/denitrification process
will remove the nitrogen from the wastewater.
The resulting effluent will meet the requirements for surface disposal
of the effluent because of the low nitrogen concentrations. Using surface disposal for effluent disposal
allows more effluent per acre to be applied to the land than is allowed during
effluent disposal by reuse. This means
less land is required. In addition,
ADEQ does not require storage ponds when surface disposal is used. This alternative allows the evaluation of
the cost to combine the flows for treatment and disposal at one treatment
plant. Discharge to Green Brush Draw
was included as an optional or emergency disposal method.
Alternative 4 was
proposed as part of the Gannett Fleming Master Plan and accepted by the City of
Bisbee.
iv. Project Justification:
This project is
crucial for the City in order to address the present and future environmental
and public health issues associated with its wastewater treatment and disposal.
The proposed facilities will greatly minimize the possibilities for
contaminating groundwater supplies. The project will assist the City in
complying with state and federal regulatory agencies, and will accommodate the
Citys future wastewater treatment needs as developed in the Master Plan. The existing facilities threaten public
health and the environment by allowing insufficiently treated wastewater to
discharge to the subsurface and possibly the groundwater, and by discharging
partially treated wastewater into Mule Gulch during rain events. High levels of
nitrates in drinking water raise significant human health concerns, especially
for infants since it can cause brain damage or death of infants. This potential
exists whenever nitrate levels exceed U.S. Public Health Service standards (10
milligrams per liter). The anticipated APP will require removal of nitrogen to
within the allowable limits, and without the new facility, the human health and
environmental issues associated with nitrogen will remain.
The total cost of the
project, based on the 70 percent engineers probable construction cost is
$30,068,000, including administrative, engineering, legal, value engineering,
bond counseling, and contingency fees. Construction costs are broken down as
follows: collection system improvements: $13,333,000; clean closure of existing
facilities: $255,000; Mule Gulch lift station and force main: $967,000; San
Jose wastewater treatment plant: $8,399,000.
4. Conformance with International Treaties and
Agreements
This project conforms
to international treaties and agreements. Furthermore, there will be no
transboundary effects from this project, as discharges will be within U.S.
territory.
1. Human
Health/Environmental Needs.
The City of Bisbee has a deteriorated wastewater collection system, and
the three existing wastewater treatment plants are not complying with the
Arizona Department of Environmental Quality standards.
2. Environmental Assessment.
The Region IX EPA prepared an environmental assessment for the project. The environmental review did not find any significant impacts resulting from the rehabilitation of the wastewater collection system or the construction of a new wastewater treatment plant in San Jose. A consultation with the Arizona State Historic Preservation Office and with the Arizona Tribes was completed. Letters of concurrence were received from both the SHPO and the Arizona Tribes. EPA issued a Finding of No Significant Impact (FNSI) on April 2003. The FNSI will be adopted in August 2003.
The EA includes the following elements:
· Discussion of the direct, indirect, cumulative and short-term positive and negative effects of the project on the environmental components of the affected area (e.g. ecosystem integrity, biological diversity, sensitive environmental habitats, and human health);
· Description of unavoidable negative impacts and actions to be taken to mitigate these impacts;
· Discussion of the environmental benefits, risks, and costs of the proposed project as well as the environmental standards and objectives of the affective area.
Since the project is located in the United States in the San Pedro River watershed, transboundary impacts are not expected.
3. Compliance with Ecology and Cultural Laws
and Regulations.
A consultation with the Arizona State
Historic Preservation Office and with different Arizona tribes was performed as
part of the environmental assessment process. The environmental evaluation of
the process indicated that there are no potential impacts, direct or indirect,
to any historical, cultural, and/or archaeological resources in the area.
1. Appropriate Technology.
This section provides
a description and an evaluation of the reasonable alternatives that were
considered to meet the City of Bisbees needs.
a) Collection and Conveyance System
Brown and Caldwell
reviewed videotapes of CCTV inspections and came with the following
recommendations based on the following criteria:
i. relative cost of rehabilitation versus replacement
ii. condition of the sewer
iii. location of the sewer relative to structures
iv. location of sewer relative to historic areas
and features
v. location of sewer relative to commercial
districts
vi. suitability for rehabilitation. maximum
slopes, minimum sewer diameters, minimum cover requirements, maximum manhole
spacing, minimum water line and sewer separations, and manhole construction
methods.)
The following methods
will be used for rehabilitation of the collection system: Cured In-Place (CIPP)
and pipe bursting. CIPP rehabilitation consists of installing a resin
impregnated sock in an existing sewer. The sock is typically inserted into the
sewer through a manhole with water pressure. After insertion, the sock (liner)
is cured-in-place with circulated hot water. After curing, the ends are cut off
the cured liner and lateral and service connections are opened with robotic
cutters. In the pipe bursting process, flexible pipe, typically High Density
Polyethylene (HDPE) is pulled through an existing sewer with a winch. Pipe
bursting is typically used to upsize the host sewer. To accomplish the
upsizing, the flexible pipe is connected to a pneumatic bursting head that
shatters the host pipe as it is pulled through. Re-establishment of lateral and
service connections is typically done through the dig-and-replace method.
Another construction technique will be replacement through open trench.
In addition to the
rehabilitation or replacement of the sewer lines, approximately 800 manholes
will be replaced or rehabilitated.
|
All units in linear feet |
||
Pipe Diameter |
New |
Rehab |
Total |
(inches) |
|
|
|
Collection and Conveyance to Treatment Plant |
|||
4 |
- |
- |
- |
6 |
- |
- |
- |
8 |
92,268 |
2,939 |
95,207 |
10 |
3,235 |
676 |
3,911 |
12 |
4,661 |
487 |
5,148 |
15 |
21,516 |
- |
21,516 |
18 |
8,246 |
- |
8,246 |
Total |
129,926 |
4,102 |
134,028 |
|
|
|
|
Effluent System From Treatment Plant |
|
||
15 |
3,034 |
- |
3,034 |
18 |
9,785 |
- |
9,785 |
Total |
12,819 |
- |
12,819 |
|
|
|
|
Total System |
142,745 |
4,102 |
146,847 |
b) Interceptor installation
In addition to the
sewer lines identified in the previous section, the following interceptors will
be constructed or rehabilitated: Warren Interceptor, Airport Road Interceptor,
and the San Jose WWTP Effluent Outfall.
The Warren Interceptor
serves as the main trunk line for the community of Warren. The Airport Road
Interceptor conveys sewage from the southern part of Warren to the south along
Airport Road approximately 11,000 feet before heading to the west approximately
8,000 where it ties into the existing San Jose Interceptor. The effluent from
the proposed San Jose WWTP will be conveyed through the proposed San Jose WWTP
Effluent Outfall approximately 2,500 feet to the south where it heads west
along Purdy Lane. The interceptor heads approximately 8,000 feet to the west
along Purdy Lane to a point approximately 2000 feet west of the the
intersection with Naco Highway where the alignment changes direction to the
south. After another 3,500 feet, the interceptor discharges into Green Bush
Draw.
c) Lift Station and Force Main
The following table
presents the design criteria for the proposed Mule Gulch Lift Station and force
main. The proposed alignment would parallel the Warren Cutoff Road south to the
Arizona Street Interceptor in Warren.
The Mule Gulch Lift Station will consist of a self-cleaning wet well
with pumps provided in a duty/standby configuration.
d) Wastewater Treatment Plant
The project consists
in consolidating the existing three wastewater treatment plants (Mule Gulch,
Warren, and San Jose) and constructing one extended aeration wastewater
treatment plant at the existing San Jose lagoons site.
The following table
presents the design parameters for the proposed wastewater treatment plant.
PARAMETER |
VALUE |
UNITS |
Average Daily Dry-Weather Flow |
0.81 |
MGD (gallons x 106) |
Peak Dry-Weather Design Flow |
1.75 |
MGD |
Peak Wet-Weather Design Flow |
2.45 |
MGD |
Maximum Monthly Flow |
1.22 |
MGD |
Total BOD |
245 |
mg/l |
Total COD |
638 |
mg/l |
TSS |
224 |
mg/l |
TKN |
54 |
mg/l |
Nitrogen (as ammonia) |
34 |
mg/l |
Soluble COD |
187 |
mg/l |
Soluble BOD |
85 |
mg/l |
Copper and lead have
been detected in wastewater samples from each of the three WWTP basins and
appear to be regional and cannot be isolated to a single source or area of
Bisbee. The sample results indicate a correlation between wet-weather flow and
an increase in the mass loading rate of copper and lead.
The following table
presents the effluent quality goals for the proposed WWTP.
Effluent Parameter |
Value |
Biochemical Oxygen Demand (BOD5) |
<15 mg/l
(design goal) <30 mg/l (monthly average) <45 mg/l (weekly average) >85% removal (monthly average) |
Total Suspended Solids (TSS) |
<15 mg/l
(design goal) <30 mg/l (monthly average) <45 mg/l (weekly average) >85% removal (monthly average) |
Fecal Coliforms |
<200 cfu/100 ml (four of seven samples) <800 cfu/100 ml (single sample maximum) |
Total Nitrogen |
<10 mg/l (regulatory requirement) 8 mg/l (alert level and design goal) |
pH (standard units) |
6.5 to 9.0 |
Total Residual Chlorine |
<5.0 mg/l
(monthly average) <11 mg/l (daily
maximum) |
Effluent will be
treated to meet anticipated NPDES requirements associated with discharge to
Green Bush Draw, and also to meet the State of Arizona Class B+ standards for
re-use of effluent for irrigation purposed on golf courses.
The extended aeration
process is a long sludge retention time (SRT) activated sludge process. It is a
non-proprietary process that offers design flexibility and custom design geared
toward local wastewater needs. The flow from the preliminary treatment
process is split between two trains of
the extended aeration activated sludge system. The flow enters the extended
aeration system by gravity. The activated sludge system is divided in two
zones: the first zone is unaerated and therefore anaerobic or anoxic depending
on the degree of recycle and it has the dual purpose of denitrification and
selecting against bulking organisms; the second zone is aerated and provides
BOD removal and nitrification.
After aeration in the
second zone, mixed liquor then discharges to a splitter box, which splits flow
between the secondary clarifiers. The operating SRT of the extended aeration
system is approximately 25 days, which is sufficient to produce a stable
biosolids end product suitable for final disposal. The clarified effluent flows
to the disinfection process.
Disinfection will be
achieved through a Ultraviolet (UV) system. Ultraviolet light comprises the
band of the electromagnetic spectrum with wavelengths between 100 and 400 nm. The
wavelengths between 200 and 300 nm are considered to be the most effective
germicidal wavelengths, with 253.7 nm as the optimal wavelength. UV
disinfection is a physical process that uses radiation to penetrate
microorganism cell walls. Cell DNA and RNA are damaged by the absorbed
radiation, which can prevent reproduction and destroys the viability of
bacteria and viruses.
2. Operation and
Maintenance
The O&M manual for the treatment plant as a whole should include the following elements:
Plan Element |
|
Description |
Start-Up Operation Plan |
|
The Operation Plan will be developed by the design engineer to ensure that Treatment plant staff understand how to properly start-up and operate the facility. Traditionally, the contractor and equipment supplier conduct the initial start-up of plant equipment to permit the detection that equipment is installed and started properly. Start-up operations and training of the permanent staff should be part of this activity. |
Contingency Plan |
|
The Contractor will be required to submit an emergency response and contingency plan covering the construction and start-up phase, upon the issuance of the contract award notice. This plan will be updated and maintained by Public Works Division personnel to cover any emergency that might occur during normal operation. |
Safety Plan |
|
A safety and health plan will be developed by the WWTP Superintendent and implemented by all Public Works Division personnel involved with plant operation and maintenance. It should include safety training before start-up, with periodic refresher training. |
Quality Assurance Plan |
|
The quality assurance plan should be developed during the start-up |
Pollution Prevention Plan |
|
The construction operator will provide a Pollution Prevention Plan, including a Storm Water Pollution Prevention Plan required by the NPDES permit. |
Facility Closure Plan and Post-Closure Plan |
|
The existing lagoons will be decommissioned during and after the start-up of the new facilities. A closure plan will be submitted to ADEQ with the facility closure application. |
3.
Compliance with applicable design norms and regulations.
Currently, Brown and Caldwell is
under contract to the City of Bisbee, Arizona to prepare final design for the
wastewater treatment plant. Seventy percent design has been completed. Also, a
Value Engineering was performed to the final design. The project is being
designed according to the State of Arizona Construction Code (ACC) (formerly
known as Bulletins 11 and 12). The ACC establishes parameters that must be followed
during design of wastewater collection and treatment systems. The Arizona
Department of Environmental Quality will review 100 percent design drawings and
specifications once they are complete in order to grant a Construction Permit.
1.
Financial
Feasibility.
A
financial model was prepared by Economist.com and was reviewed by the NADB to
determine the adequate financial structure for the project. The project costs
are presented in the table below.
Concept
|
Cost
|
Planning and Design
|
4,066,000 |
Project Management
|
500,000 |
Financial Council
|
313,000 |
Easements/Land
Acquisition
|
135,000 |
WWTP *
|
8,399,000 |
Lift Station and
Force Main*
|
967,000 |
Wastewater
Collection System*
|
13,333,000 |
Construction Phase Services |
2,100,000 |
Closure of Existing
WWTP
|
255,000 |
TOTAL |
30,068,000 |
*
Includes a 10 percent contingency;
The following funding
sources were identified to cover the project costs:
Funding Source
|
Amount
|
USDA Rural
Development Loan |
3,050,000 |
Arizona Water Infrastructure
Finance Authority Loan |
11,250,000 |
Border Environmental
Infrastructure Fund Grant |
10,213,000 |
USDA Rural
Development Grant |
3,050,000 |
Border Environment
Cooperation Commission Grant |
505,000 |
City
of Bisbee Contribution |
2,000,000 |
TOTAL
|
30,068,000 |
The
project also includes a $1,100,187 grant from the Border Environment
Infrastructure Fund as transition assistance to be applied directly to
subsidize user fees.
2. User Fees
The proposed residential user fee
structure resulting from this project is as follows:
Year |
User Fee (in dollars per month) |
2003 (Current) |
24.64 |
2004 |
25.87 |
2005 |
26.91 |
2006 |
27.85 |
2007 |
28.82 |
2008 |
29.83 |
2009 |
31.03 |
2010 |
32.58 |
2011-2019 |
34.21 |
3. Project
Management.
The project implementation will be
responsibility of the City of Bisbee. The City will also be responsible for
operation of the infrastructure.
1.
Comprehensive Public Participation Plan.
The
projects public participation plan was submitted and approved in early 2001.
It was developed in coordination by the City of Bisbee, project steering committee.
It includes the elements required for public participation such as a developing
a steering committee, contacting local organizations, providing public access
to project information and holding public meetings. A summary of these
activities is presented below.
2.
Steering Committee
The project steering
committee was formed in January 2001 with local citizens and members the
Wastewater Advisory Committee who helped guide the successful ½ % sales tax in
November 2000. Its membership includes:
Jim Burke, Curator, Bisbee Mining & Historical Museum; John Charley; City
Councilperson; Luche Giacomino, City Councilperson; Carrie Gustavson, Director,
Bisbee Mining & Historical Museum; Bill Jenning, citizen (retired); Donna
Harris, Director, Bisbee Chamber of Commerce; Dennis Nelson, City
Councilperson; Charlie Sotelo, a local realtor; Bob Downing of the Planning and
Zoning Commission; and Stanley Stern a Financial Consultant. The committee
decided to have four facilitators/leaders for the Committee: Donna Harris, Carrie Gustavson, Dennis
Nelson, and Charlie Sotelo. Jim Burke served as the recording secretary. The
Technical Work Group consisted of Suzanne Price, WIFA outreach coordinator; Dan
Beauchamp, mayor, City of Bisbee; Susan Keith, SE
Arizona Community Liaison, ADEQ; Alan OBrien,
consulting engineer and Susan
Zeloznicki, Public Participation consultant to City of Bisbee.
3.
Local Organizations
The following key
organizations were identified and approached to support the wastewater
improvements project: the Bisbee Womens Club; Bisbee Repertory Company; Bisbee
Arts Council; Boys and Girls Club; Chamber of Commerce; Church Council and
other church groups; Copper Queen Hospital Association; Council of Arts and
Humanities; County Board of Health; County Board of Supervisors; Democratic
Club; Design Review Board; Kiwanis; Parks & Recreation Commission; Phelps
Dodge; Planning & Zoning; Rotary Club; the Bisbee Unified School District
#2; Bisbee Senior Association and St. Patricks Church. Twelve letters of
support were received.
5.
Project information
The official documents were
available at the local library, Chamber of Commerce and City Hall 30-days prior
to the first meeting during normal business hours until 7PM including Saturdays
an Sundays. A media and information campaign was carried out which included
contacting local and regional TV stations, radio and newspapers; mail out of
fact sheets and brochures and outreach activities at public events.
5.
Public Meetings
Public meetings were held on April 10, 12, 18 and March 6,
2001 where technical and financial components of the project and debt
authorization election were discussed.
Videotapes of these public meetings were aired on public access
television. A final public meeting was held on August 6, 2003 to present the
rates to the community.
6.
Debt Authorization Election
The debt authorization election was held on May 15, 2001. More than 30% of the towns voters went to the polls. The measure was approved by 95% of the voters.
1. Definition and
Principles
The project is
consistent with BECCs definition of sustainable development: conservation oriented social and economic
development that emphasizes the protection and sustainable use of resources,
while addressing both current and future needs, and present and future impacts
of human actions and with the
four principles:
a) Human
beings are at the center
they are entitled to a healthy and productive life in
harmony with nature. This principle is
addressed by the purpose of the project, which is to address health risks
associated with the present inadequate capacity of the existing City of Bisbee
facilities. Healthier lives and better
living conditions will result from this project.
b)
The right to development
equitably meet
needs
of present and future generations. The
construction, expansion and upgrading of the City of Bisbee facilities will
accommodate growth projected through the year 2020, while addressing a critical
need today.
c)
environmental protection shall constitute an
integral part of the development process
All environmental parameters have been met. The City of Bisbee has been careful to ensure that natural
resources are protected, plant and animal species of concern are not impacted,
and cultural heritage issues are recognized. Also, the City of Bisbee in
cooperation with the AWC has implemented a reuse program where treated effluent
will be used for golf course irrigation.
d)
The
stakeholders
must be part of any related activity. Stakeholders have been a part of the process
since the early part of the project development. Public participation and
outreach programs have ensured that public input has been received, considered
and employed.
2.
Institutional and Capacity Building
The new expansion will allow the City of Bisbee facilities to
provide necessary quality of life services for its residents. In order to minimize the additional
operational burden to the Community, the technology chosen is the required of
typical facilities in use today. The
project will allow the City of Bisbee to meet all regulatory requirements
relative to wastewater treatment to comply with the State of Arizona APP. Additionally, the project includes the
review and update of necessary tariffs for the efficient operation of the
utility.
3. Conformance with Applicable Local and
Regional Conservation and Development Plans
The project will
assist the City in complying with state and federal regulatory agencies, and
will accommodate the Citys future wastewater treatment needs as developed in
the Master Plan. Furthermore, this
project is of high priority for ADEQ since it has been way long time since any
improvements on sewer services took place for the City of Bisbee resulting on
the backwardness on wastewater infrastructure mainly caused for a service
connection moratorium that last for years and with the proposed action
implementation will be reactivated. The
project also is consistent with the Citys General Plan in relationship to
providing adequate wastewater collection and treatment.
4. Natural Resource Conservation
The implementation of
the project will enable the City of Bisbee to keep collecting and treating
adequately the wastewater generated in the community, it will minimize the risk
of polluting soil and groundwater.
Also, the reuse program will be improved by providing recycled water for
the golf course that will contribute to the natural resources conservation.
5. Community Development
The new wastewater treatment plant can have a positive impact for the City of Bisbee by helping to provide improved services and environmental conditions that can attract new businesses and allowing new connections to the wastewater collection system.
In sum, the economic activity will increase and the quality of life will improve due to the implementation of the project.